All projects
Illustration
Deployed
WMS Reflex deployment
From a 100% paper warehouse to a stabilized WMS, at Pillaud Matériaux.
IllustrationContext
Building materials distribution. I was both Supply Chain Director and WMS project lead, with a team of 10.
Challenge
Implement a WMS from scratch on processes that were not yet mature, with strong resistance to change to anticipate.
Actions
- Specifications, tender and selection of Reflex
- Administrator training and project team management
- Budget and schedule tracking, workshops and configuration
- Test book, test validation and dry run
- Team training and go-live on 12/01/2025
- RUN stabilization and adjustments for 3 months
Results
- −30%
- errors and disputes
- +30%
- inventory productivity
- +30%
- storage occupancy
- −50%
- onboarding time
Results observed on this project, with no guarantee for another context.